1. If one of the parties to a bilateral contract breaches a contractual obligation, then the other party to the contract may repudiate the contract if the obligation is not performed within an additional period of time fixed by him/her. If, based on the nature of the breach, no additional period of time is afforded, then a warning shall be equivalent to the fixing of an additional period of time. If the obligation is breached only in part, then the obligee may repudiate the contract only if the performance of the remaining part of the obligation is no longer of any interest to him/her.
2. An additional period of time need not be fixed or a warning need not be issued when:
a) it is obvious that it will yield no results;
b) the obligation was not performed within the period of time fixed under the contract, and the creditor has in the contract tied continuation of the relation to the timely performance of the obligation;
c) an immediate termination of the contract is justified for specific reasons, in the mutual interests of the parties.
3. A contract may not be repudiated if:
a) the breach of an obligation is insignificant;
b) the requirements of Article 316(2) have been violated and, notwithstanding that, the obligee may be required to maintain the contract in force;
c) the obligee himself/herself is fully or principally liable for the breach of the obligation;
d) there is a counterclaim against the claim of breach, which the obligor has already asserted or will assert immediately after the repudiation of the contract.
4. The obligee may repudiate the contract before the due date of performance if it is obvious that reasons for repudiation will occur.
5. The obligor may determine a reasonable period for the obligee to repudiate the contract.